1 Committee organization
and procedures
1.1 Membership
and attendance
Self-introductions were made, attendance taken, and it was determined
that a quorum was present.
1.2 Approval
of the Agenda
The Committee unanimously accepted the Agenda as presented.
1.3 Approval
of the Minutes
The Committee
unanimously accepted the Minutes of the last meeting as written.
1.4 Correspondence
No correspondence was received.
ACTION ITEM -
1.5 Review of
the Committee's scope
No review was needed.
1.6 Report of
task groups and DSCC efforts
A DSCC report from G-11 working group, FSC 5950, was distributed to
the attendees
2 Old business
2.1 Multilayer
bead specification status
Copies of PN4315 was handed out to attendees for review and comments.
Comments were received and marked. (C Jackson) will incorporate changes
and send copy to (B Gisseler) within 30 days. (B Gisseler) will insure
that all attendees receive a copy of PN4315 and ask for additional comments
of revision to spec. All comments are to be received prior to the next
meeting. (B Aronson) also stated that he would send a copy of ANSI J-002
to (B Gisseler)
2.1.1 Vote on
acceptance of PN4315
(B Gisseler) states that the plan is to vote on PN4315 during October,
2000 meeting.
ACTION ITEMS:
-send copy of ANSI J-002 to B Gisseler
-Marked up copy of PN4315 to be sent to B Gisseler within 30 days of
meeting
-All comments from attendees for PN4315 to be submitted before Octorber
2000 meeting
-Vote on acceptance of PN4315
2.2 Attachements
from Previous meeting, October 1999.
(B Aronson) indicated that the attachements, if in electronic form,
from the previous meeting, which were not attached with the minutes,
would be sent out within 7 days from 04 April, 2000.
ACTION ITEMS:
-B Gisseler to insure attachements have been sent
2.3 Status of
PN4233
(B Aronson) indicated that PN4233 did not appear to be a valid PN#.
(B Aronson) to confirm status of legitimacy.
ACTION ITEMS:
- B Aronson to report on status
2.4 Merging of
Wirewound and multilayer inductor specs
Copy of original merged copy was unavailable. (B Aronson) to look for
and send copy of previous merged spec, if he still has it, and send
to (B Gisseler) and (B Friedman). (B Gisseler) and (B Friedman) to head
up merging of wirewound and multilayer specs into one specification.
(B Gisseler) to follow up with (B Aronson) to see if he can sned spec
to (B Friedman) and (B Gisseler).
ACTION ITEMS:
-B Gisseler and B Friedman to have merged copy ready for review by October
2000 meeting
2.5 EIA/IS 759
& EIA/IS 760
(B Aronson) indicated that these specifications have previously been
approved by committee
2.6 Minutes from
04 April, 2000 P-3 meeting
(B Gisseler) to follow up in June 2000 to insure minutes and attachements
have been sent to attendees. The committee also stated that the minutes
and attachments should be sent to attendees 30 days after meeting.
ACTION ITEMS:
-B Gisseler to insure minutes of meeting were sent within specified
time frame
2.7 Submission
of package sizes
(M Griffith) to resend electronic copy of part dimensions and land pattern
dimensions to (B Aronson) and (B Gisseler) by 11 April 2000.
ACTION ITEMS:
-(M Griffith) to send electronic copy to (B Aronson) and (B Gisseler)
2.8 HP/Agilent
HP4287A test equipment and fixture 16196 A/B/C presentation
(J Bradshaw)
presented information on new test equipement to insure high repeatability
testing of 0201, 0402 and 0603 inductors
3 New business
3.1 Inductor
application guide
Discuss whether application guide should be started
4 Selection of
next meetings
Mon-Wed., 2-4 October 2000, San Diego, California @ Wyndham Emerald
Plaza
5 Adjournment
The Committee moved, seconded, and unanimously agreed to adjourn at12:30pm
6 Action items
-send copy of ANSI J-002 to B Gisseler
-Marked up copy of PN4315 to be sent to B Gisseler within 30 days of
meeting
-All comments from attendees for PN4315 to be submitted before Octorber
2000 meeting
-Vote on acceptance of PN4315
-B Gisseler to insure attachements have been sent
-B Aronson to report on status
-B Gisseler and B Friedman to have merged copy ready for review by October
2000 meeting
-B Gisseler to insure minutes of meeting were sent within specified
time frame
-(M Griffith) to send electronic copy to (B Aronson) and (B Gisseler)
This meeting was
conducted in accordance with the EIA legal guidelines and the manual
of organization and procedures.